Overhead Cranes Explained: Runway Alignment and Load TestingNow

In large construction and fabrication spaces, overhead/bridge cranes do the heavy lifting—literally. This practical guide shows how a full overhead crane system comes to life inside a structural building. We’ll kiewit construction cover rails and runway alignment—with the same checklists pro installers use.

What an Overhead/Bridge Crane Is

An overhead crane rides on parallel runways anchored to a building frame, with a trolley that travels left-right along the bridge and a hoist that lifts the load. The result is smooth X-Y-Z motion: cross-travel along the bridge.

They’re the backbone of heavy shops and assembly lines, from beam handling to turbine assembly.

Why they matter:

Safe handling of very heavy, unwieldy loads.

Less manual handling, fewer delays.

Repeatable, precise positioning that reduces damage.

High throughput with fewer ground obstructions.

What This Install Includes

Runways & rails: continuous beams and rail caps.

End trucks: motorized gearboxes for long-travel.

Bridge girder(s): single- or double-girder configuration.

Trolley & hoist: reeving, hook block, upper limit switches.

Electrics & controls: VFDs, radio remote, pendant.

Stops, bumpers & safety: end stops, buffers, travel limits.

Depending on capacity and span, you may be dealing with modest shop lifts or major industrial picks. The choreography is similar, but the scale, lift plans, and checks grow with the tonnage.

Pre-Install Prep

A clean install is mostly planning. Key steps:

Drawings & submittals: Freeze the GA and verify reactions with the structural team.

Permits/JSAs: Job Safety Analysis (JSA) for each lift step.

Runway verification: Check baseplates, grout pads, and anchor torque.

Power readiness: Lockout/tagout plan for energization.

Staging & laydown: Lay out slings, shackles, spreader bars, and chokers per rigging plan.

People & roles: Appoint a lift director, rigger, signaler, and electrical lead.

Millimeters at the runway become centimeters at full span. Measure twice, lift once.

Rails & Runways

If rails are off, nothing else will run true. Targets and checks:

Straightness & elevation: Laser or total station to set rail height.

Gauge (span) & squareness: Check centerlines at intervals; confirm end squareness and expansion joints.

End stops & buffers: Verify clearances for bumpers at both ends.

Conductor system: Mount conductor bars or festoon track parallel to the rail.

Log final numbers on the ITP sheet. Correct now or pay later in wheel wear and motor overloads.

Girder Erection & End Trucks

Rigging plan: Softeners protect painted flanges. Dedicated signaler on radio.

Sequence:

Install end trucks at staging height to simplify bridge pick.

For double-girder cranes, lift both girders with a matched raise.

Land the bridge on the end trucks and pin/bolt per GA.

Measure diagonal distances to confirm squareness.

Prior to trolley install, bump-test long-travel motors with temporary power (under permit): confirm limit switch wiring. Lock out after test.

Cross-Travel Setup

Trolley installation: Hoist/trolley arrives pre-assembled or as modules.

Hoist reeving: Lubricate wire rope; verify dead-end terminations.

Limits & load devices: Set upper/lower limit switches.

Cross-travel adjustment: Verify end stops and bumpers.

Pendant/remote: Install pendant festoon or pair radio receiver; function-test deadman and two-step speed controls.

Grinding noises mean something’s off—stop and inspect. Don’t mask issues with higher VFD ramps.

Drive Tuning & Interlocks

Power supply: Conductor bars with collectors or a festoon system.

Drive setup: Program VFDs for soft starts, decel ramps, and brake timing.

Interlocks & safety: Zone limits near doors or mezzanines.

Cable management: Secure junction boxes; label everything for maintenance.

Future you will too. Photos of terminations help later troubleshooting.

QA/QC & Documentation

Inspection Test Plan (ITP): Third-party witness for critical steps.

Torque logs: Re-check after 24 hours if required.

Level & gauge reports: Note any corrective shims.

Motor rotation & phasing: Confirm brake lift timing.

Functional tests: Anti-collisions and zone interlocks.

A tidy databook speeds client acceptance.

Load Testing & Commissioning

Static load test: Apply test weights at the hook (usually 100–125% of rated capacity per spec).

Dynamic load test: Check sway, braking distances, and VFD fault logs.

Operational checks: Emergency stop shuts down all motions.

Training & handover: Maintenance intervals for rope, brakes, and gearboxes.

Only after these pass do you hand over the keys.

Everyday Heavy Lifting

Construction & steel erection: handling long members safely.

Oil & gas & power: generator and turbine assembly.

Steel mills & foundries: hot metal handling (with the right duty class).

Warehousing & logistics: bulk material moves with minimal floor traffic.

Floor stays clear, production keeps flowing, and precision goes up.

Controls that Matter

Rigging discipline: dedicated signaler and stop-work authority.

Lockout/Tagout: clear isolation points for electrical work.

Fall protection & edges: scissor lifts and manlifts inspected.

Runway integrity: regular runway inspection plan.

Duty class selection: match crane class to cycles and loads.

Safety isn’t a stage—it's the whole show.

Keep It Rolling

Crab angle/drift: re-check runway gauge and wheel alignment.

Hot gearboxes: adjust brake air gap and reduce VFD decel.

Rope drum spooling: check fleet angle and sheave alignment.

Pendant lag or dropout: shield noisy VFD cables.

Wheel wear & rail pitting: lubrication and alignment issues.

A 10-minute weekly check saves days of downtime later.

Quick Answers

Overhead vs. gantry? Bridge cranes ride fixed runways; gantries walk on the floor.

Single vs. double girder? Span and duty class usually decide.

How long does install take? Scope, bay readiness, and tonnage rule the schedule.

What’s the duty class? FEM/ISO or CMAA classes define cycles and service—don’t guess; size it right.

Who Gets the Most Value

If you’re a civil or mechanical engineer, construction manager, shop supervisor, or just a mega-project fan, this deep dive makes the whole process tangible. You’ll gain a checklist mindset that keeps cranes safe and productive.

Need a field bundle with JSA templates, rigging calculators, and commissioning sheets?

Get the toolkit now so your next crane goes in cleaner, faster, and right the first time. Save it to your site tablet for quick reference.

...